LiLo System · Delivery Planning

Delivery Schedule · Jul 6 → Aug 1 2026

Two engineers. Monday clears the decks (every remaining in-progress slice closed, plus one new WU each), then new WUs run at 3/day per engineer (6/day) open-to-goal. Ownership: Ryan → INST + PROP, Yash → DERIV + UA + NOTIF; Yash is barred from INST-PIPE-WU≥07 / INST-WU≥06. Live tracker, CTO re-plan Sun Jul 12: 37 done, 3 in progress, the rest to do. Week 1 is reconciled to shipped reality (the Sat Jul 11 catch-up column holds six Done WUs). Week 2 is the build run D6 → D10 plus a Ryan build-Saturday (Jul 18) that absorbs the on-hold and placeholder UA tail, so nothing spills into week 3 and the Stabilize → Ship window stays clear.

Family

UA
INST
PROP
DERIV
OPR
NOTIF
HUB
INFRA
Done
In progress
To do
Monday closure slice